I thought I'd provide an update for institutions that are told their instance will be moved. We had a few issues:
- We delayed until after school was out, but while teachers were still working on grades. We had a few teachers experience error messages when they attempted to log in at the same time the move was taking place. We elected not to notify our users ahead of time. I might rethink that decision.
- The connection to our Data was lost and lost for a long time. We notified Instructure we were experiencing an error message in the Data screen indicating the connection had been lost. I was told it would be restored in a few days, but following that we lost access to the Data screen entirely. It took Instructure a few months to restore this. My opinion is this issue slipped through the cracks due to the July timing and InstructureCon preparations. The Data access authorizations had to be redone, which didn't take much time for us.
- Most of our LTI links restored themselves upon login, but not all. Badgr is an example of one that needed to be restored. Might be a good idea to let the vendors know this is happening in case errors come up later.
- We had an issue with our API loads the first time following the move because of a lost token, but once that was restored everything ran.
For the most part, it went smoothly. I didn't hear of lost data, but this easily could have gone unreported since the move was done after the school year ended.
Hope this helps!