I am grading my class completing SITXMGT001 - Monitor Work Operations. I need help with the following 2 questions in the case study as most students are getting these wrong and there are no calculations in the answers. Please advise me of the calculation so I can assist my students is getting the correct answers.
Q15. Next week, projected beverage sales are $56,500: you overall labour cost percentage is 17% of sales. What should your maximum roster cost be for this period?
- $9,605.00.
Q16. You have just costed your roster for the bottle shop for next week and found wages will cost you $11,421. What sales will you need to achieve to meet your 9% labour cost percentage target?
- $126,900.
Many thanks,
Fran Cumming.